Site C is a shallow soil and groundwater impact site, its primary COCs are metals and VOCs (soil) and lead (groundwater). Completed soil cleanup actions include characterization, excavation, sorting, treatment, disposal, site restoration, site access restrictions, and groundwater. One cleanup action, implementation of LUCs, is ongoing. Groundwater containment and discharge of extracted water have been completed for Site C, while groundwater/surface water monitoring and LUCs are ongoing.
Site D is a deep soil and groundwater impact site, its primary COCs are VOCs (including TCE) for both soil and groundwater. Ongoing groundwater cleanup actions include hydraulic containment and contaminant removal from the source area, groundwater treatment, treated water discharge, institutional controls, review of new technologies to help address affected groundwater, and groundwater monitoring. Completed soil cleanup actions include restricted site access, soil vapor extraction (SVE) system treatment, maintenance of existing site caps, maintenance of surface drainage controls and characterization of shallow soil and dump. Ongoing groundwater monitoring is being implemented as a part of sitewide OU2 deep groundwater monitoring.
Site E is a shallow soil impact site, its primary COCs are metals. Completed soil cleanup actions include characterization, excavation, sorting, treatment, disposal, site restoration, site access restrictions, and groundwater monitoring. One cleanup action, implementation of LUCs, is ongoing.
Site G is a deep soil and groundwater impact site, its primary COCs are VOCs (including TCE) for both soil and groundwater. Ongoing groundwater cleanup actions include hydraulic containment and containment removal from the source area, groundwater treatment, treated water discharge, institutional controls, review of new technologies and groundwater monitoring. Completed soil cleanup actions include restricted site access, SVE system treatment, maintenance of existing site caps, maintenance of surface water drainage and characterization of shallow soils and dump. Ongoing groundwater monitoring is being implemented as a part of sitewide OU2 deep groundwater monitoring.
Site H is a shallow soil impact site, its primary COCs are metals. Completed soil cleanup actions include characterization, excavation, sorting, treatment, disposal, site restoration, site access restrictions, and groundwater monitoring. One cleanup action, implementation of LUCs, is ongoing.
Site I is a shallow and deep groundwater impact site, its primary COCs are VOCs. Ongoing shallow groundwater remedial actions include groundwater monitoring and LUCs. Ongoing deep groundwater cleanup actions include hydraulic containment and contaminant removal from the source area, groundwater treatment, treated water discharge, institutional controls, review of new technologies to help address affected groundwater, and groundwater monitoring.
129-3 is a shallow soil impact site, its primary COCs are metals, nitroglycerin, and VOCs. Completed soil cleanup actions include characterization, excavation, sorting, treatment, disposal, site restoration, site access restrictions, and groundwater monitoring. One remedial action, implementation of LUCs, is ongoing.
129-5 is a shallow soil impact site, its primary COCs are metals. Completed soil cleanup actions include characterization, excavation, sorting, treatment, disposal, site restoration, site access restrictions, and groundwater monitoring. One cleanup action, implementation of LUCs, is ongoing.
129-15 is a shallow soil impact site, its primary COCs are lead and polycyclic aromatic hydrocarbons (PAHs). Completed soil cleanup actions include characterization, excavation, sorting, treatment, disposal, site restoration, site access restrictions, and groundwater monitoring. One cleanup action, implementation of LUCs, is ongoing.
The Grenade Range is a shallow soil impact site, its primary COCs are metals. Ongoing cleanup actions include implementation of LUCs.
The Outdoor Firing Range is a shallow soil impact site, its primary COCs are metals and PAHs. Ongoing cleanup actions include implementation of LUCs.
MNARNG EBS is a shallow soil impact site, its primary COCs are PAHs. Ongoing cleanup actions include implementation of LUCs.
135 PTA is a shallow soil impact site, its primary COCs are PAHs. Ongoing cleanup actions include implementation of LUCs.